Warren School
PROJECT OVERVIEW:
Create 2 FA spec grass football pitches at no cost to the school.
REASON FOR UPGRADE:
As part of a land swap the school were trading 2 very poor condition pitches for arable land on condition new pitches were created.
CLIENT:
The Crown
CLIENT OBJECTIVE:
To help conclude one deal whilst at the same time adding tremendous benefit the school.
PROJECT LENGTH:
1 year from start to finish.
PROJECT SIZE:
The project covers 3 acres and involves the importation of 60,000 m3 of environmentally approved soil.
THE PLANS:
The finished project will include the following …
- 2 FA spec grass football pitches, including 10-metre lateral drainage and sand injection. Pitches were only handed over after a thorough maintenance program to ensure they were in excellent condition at hand over. The pitches were also white lined prior to hand over.